Thursday, August 25, 2016

Work and Play

Its been two weeks since we have been in Ghana. It is hard to tell if Ghana is our home or New York....

After week filled with stress and hard work, we have started the week off with relaxing trip to Volta Region. It was well deserved rest but we are back in business!


This week started with the development of the Borzey House well, as well as the pump tests of both of the new wells. The Primary School has yield of 24 L/min, and the Borzey House well has the yield of 32 L/min. This gives us the total yield of 56 L/min. This yield is below our predicted yield, which could be partially accounted to the shale rock which was present at the sites instead of the predicted granite and gneiss based on the geological maps of Ghana that were available to us. We also had some difficulty with our contractors rushing to finish the wells, which caused the Primary School well to be fairly shallow (the absolute minimum of our design).





This week, we have also ventured out to Nsawam to purchase one tank for the submersible pump, as well as pipes, connectors, and all other equipment. We chose to "recycle" an unused tank by the latrines. This ordeal ended with one member of the Unit Committee going into the tank to unscrew it from its original location. He did not hesitate at all, he just disappeared inside.




We have also constructed temporary concrete platforms for the tanks at both sites. We quickly realized that the concrete blocks were very heavy. We struggled to carry one block with two people, while the mason casually transferred the blocks from the stock to the construction site. We had so much fun balancing...I mean we did our fair share of work compacting the cement and gravel of our platforms. Yes, hard labor indeed.



(Ok we actually dug pits for the pipes)

After 6 hour deliberation with our main contractor, we have finalized and signed the second contract to install the submersible pumps for the new boreholes. Next on our radar is the Electricity Company, as the pumps will need to the connected to electricity.

Thank you for reading the update,
EWB Columbia University Ghana Summer 2016 Travel Team


Saturday, August 20, 2016

The Electric Well

It’s been one week since we arrived in Ghana, and we were joined today by the last member of the travel team, Heather Morriss, coming to us from Germany. It already feels like so much longer, and we have been truly adopted as members of the community.

On Thursday, the drilling rig arrived in Amanfrom and drilled both wells. The rig showed up early, at 7:50 am, and began drilling the Primary School Well. The drillers were using an air rotary drill, in which compressed air blows the cuttings to the top of the borehole as the drill stem advances to greater depths. As a result, the drilling process is very dusty initially, but stops once water is encountered. The drillers provided us with a shovelful of drill cuttings representing each meter that the drill stem had advanced, so that we could make observations about the geology. The children gathered to watch the drill, and screamed in excitement when the water began shooting out once the drill reached a depth of 21 meters. Water seemed to be primarily in the deeper crystalline geologic formation (most likely fractured granite or gneiss), rather than the overlying shale formation. We continued to drill until 60 meters, which was the minimum in our designs. The well was briefly developed by shooting compressed air into the bottom of the borehole, causing the formation water to rush to the surface and create a fountain of water 10 meters into the air. “Development” in the context of well construction means removing any fine particles which may have been introduced into the subsurface by the drilling process, as these particles can clog the water-bearing fractures and the well screen. Even the adults, including the EWB team, were excited to see the geyser we had created! To keep the children away from the built well, Sammy told the kids that the drillers poured electricity into the borehole, and they must stay away so they don't get shocked. This worked at first, as no one was spotted anywhere near the well while we were relocating to the second drill site.

Drilling at the Primary School Premises 

The full array of Primary School well rock


We moved to the Borzey House to start drilling immediately after developing the first well. Drilling 11:30 am. Unlike the Primary School well, we did not find much evidence of water, as the shale formation extended the full depth, and the crystalline formation was not encountered. We drilled to our maximum designed depth – 100 meters – and the borehole still had not produced flowing water, only moist intervals which could indicate the presence of water bearing fractures which have been blocked by drill cuttings. We then had to decide if we wanted to drill deeper, hoping we could get to more water, or do hydro-fracking (which was recommended to us by the contractor). We gave the borehole 1 hour to recharge, and some water did come up. We decided to drill an additional 20 meters, at additional cost, in hopes that more fractures would be intersected by the boring.

Drilling at the Borzey House

Unfortunately, following this decision, the contractor proceeded to change the screen in our design to an open borehole without consulting us.  This caused some tension between the team and the contractor, as they decided on their own to change the design of the well. The contractor failed to communicate effectively to us the reason for the design change or how it worked.  They also were rushing to complete both wells in a single day, without adequate time for communication and consideration of options.  We believe this was because they didn't want to return with the full drilling crew the second day. Luckily our technical mentor, Joelle Freeman, is a professional hydrogeologist with well drilling experience, so we stopped the construction of the well until we were all in agreement on the design. We ended up with a approving a modification to an “open borehole” below 42 meters of unslotted PVC. The end of the pipe is “fanned” out to keep washed gravel from going down to the end of the borehole. The bedrock that is exposed from 42 meters to 120 meters should have minimal fine sediments after the well is developed, allowing the water to enter the borehole and remain clear. 

In the evening, the children who had been watching the slow progress of drilling the Borzey House well, proudly announced that they had tested to see if the Primary School Well had electricity!  They all laughed so hard and said, no one was shocked, we are not afraid! So, since we were caught trying to trick them, we told them the truth, that there is no electricity, but they must not disturb the well until it is complete. We were still working after the light had gone, so the constructor left before developing the well. The Borzey House well will be developed within the next few days, most likely using the same submersible pump that will be used to conduct the yield test. We are waiting for the yield test results to finalize the design of each well.

On Friday we also ventured out to Aburi to meet with the South Akwapim District Assembly. After a long and somewhat overwhelming Ghanaian government structure crash course, we presented our designs. The District Assembly was very interested in our designs and asked insightful questions. They ensured us that they will supervise the villagers and the Amanfrom Unit Committee to make sure the system is up and running even after we are long gone. The Assembly also was very interested in forming a partnership between Columbia University and the district for further projects.

The team in Aburi

We have also briefly visited Obodan, to monitor and study the water system that the Chapter previously constructed. We were pleasantly surprised at the condition of the water system. Three years later, all parts are functioning, and vegetation has grown back to protect the pipes from erosion. We also saw that the villagers modified the spigots so they can fill their heavy buckets with water, while it is already on their heads! This eliminates the need for a second person to assist with lifting the heavy bucket from the ground.  We were very impressed that the Obodan Water and Sanitation Committee took initiative and derived such a clever solution to the problem! Engineering for the win! We also learned that the income from the fees for water from the Obodan water system (10 pesewas per bucket) has provided a reliable source of income for the Unit Committee to use towards other projects. Particularly impressive is that the money was used to raise a 5% contribution for the construction of a new Junior High School by the Blue Skies Foundation. The new Obodan J.H.S. is now one of the nicest schools in the entire Eastern Region. We hope our water distribution project in Amanfrom will be as successful, and that the income from the system can be used for future community development projects as it has in Obodan.

Thank you for reading our update,
EWB Columbia University Ghana Travel Team 2016


P.S. Ghanaian Bars are called Drinking Spots...not that I would know.

Tuesday, August 16, 2016

Greetings from Ghana!

Ete sen! (Hello!)
EWB Ghana Travel Team 2016

The first travel team (Anna Libey, Sejal Jain, Juliet Kirk, Paulina Babiak, and our wonderful mentor Joelle Freeman) has arrived this Saturday. The last few days have been very productive and we would like to share our discoveries!

For the unfamiliar with the project, the main goal for our trip is to implement two wells in Amanfrom, which will be located by the Amanfrom Primary School and at "Borzey's House," a point near the center of the village, that is easily accessible to the villagers. We are also on a mission to Obodan, the site of our previous project, to monitor the latrines built on the previous trips. Additionally, we are surveying Amanfrom for future projects.

From the start, Anna and Sejal (who coming from Mumbai arrived about 10 hours before the rest of the team) met with the Multi-Hydro Technique Ltd. in Accra to speak with them for the first time in person about drilling the boreholes for the well. They have informed us that while the hand pump is feasible, if the borehole becomes too deep, it might become too heavy to pump for children and women (the ones usually burdened with the task of retrieving water). They suggested using Submersible Pump (electrical pump which pumps all the water to the tank so people could access the water straight from the tank).

The next day, after the rest stragglers arrived, we have surveyed the sites obtained by a geologist on the previous trip, to make sure our coordinates match up, as well as show the sites to the new members who have not traveled here before. We have encountered an issue with the GPS coordinates, as the well that would be build on the Primary School premises did not match up. Immediately, we have checked the reports and contacted the constructor who performed the original survey to make sure the spot is correct (even 10 meters could make a huge difference in the well yield!).

The future borehole sites:

The "Borzey House" Site

Amanfrom School Premises Site

After the initial survey and sightseeing of the village, we had a meeting with the Council of Elders who officially welcomed us to Amanfrom. After renaming Anna to the Anan, we have presented them with our project, and insighted them with their responsibilities and the responsibilities of the community to preserve the well and make it last as long as possible. The Elders ensured us of their cooperation, and ensured us that the Water Committee will this time work to make the project possible. The meeting concluded with us taking some stylish pictures with the Elders. We plan to meet with them again next Sunday to update them on the wells, and hopefully to receive a Ghanaian names (I want one too!).

Officially handing over the project to the Village!

The Council of Elders, the Chief of the Village, and the Team.

The next day, we ventured out to Accra, to meet with Multi-Hydro Drilling Company, to drill out (haha) final details of the contract. They have agreed to just drill the boreholes for the well first, before signing a contract for pump. This allowed us to have more time to research the pumps, and contact EWB about change in our design. Our mentor, Joelle, our in country contact, Sammy, and the Multi-Hydro project managers headed to the sites to survey them for the feasibility of the track with the drill to come through. We were ordered to remove one tree branch to clear the pathway.

After the survey, we came back to Multi-Hydro and we signed the contract. MAY THE PROJECT OFFICIALLY PROCEED!

We are awaiting for the last wire transfer from EWB to start drilling.

All the best,

EWB Ghana Travel Team 2016